Woodridge School

Most Aggressive Timeline / Schedule

Photos by: John Hrnchar

Messina Floor Covering, LLC

Design by Hasenstab

Cuyahoga Falls, OH
June 15, 2018 - July 30, 2018

Details:

The time frame of project ran from June 25, 2018 to July 27, 2018 - a short 5 week timeline. We were not able to work over the holiday, so we worked long hours to complete this project which included the installation of 40,000 Sq LVT, 950 yards of carpet tile, 17,000 lft of rubber cover base, and 96 stair treads.

Suppliers:

Armstrong
Tarkett
Schoenox