Hall of Fame Village - Tom Benson Stadium Phase 2

Most Aggressive Timeline / Schedule

Photos by: Hall of Fame Website

Messina Floor Covering, LLC

Design by HSK

Canton, OH
8/3/2017

Details:

The project timeline was 6/27/2017-8/3/2017 We installed 50,400 SF of flooring and 18,200 LF of wall base. Project was very involved as there were 7 levels that had to completed prior to the Hall of Fame Game.