The Mart 2.0

Most Aggressive Timeline / Schedule

Photos by: Skender

Flooring Resources Corporation

Design by Gensler

Chicago, IL
5/30/2023

Details:

This installation was in one of the largest office buildings in the world.There was regular heavy traffic with a very challenging, tight timeline - we completed our work in about 2 weeks. Despite a flood during the installation, we held to our schedule.There was over 12,000 SF of Plae Fitness Flooring which is a 4 layer system with underlayment. We delivered 15+ full truckload deliveries due to size and weight of the material. We sometimes delivered three truckloads to the site per day.-Over 1,600 LF of Johnsonite base-MAPEI and XL Brand products were used-Over 1,200 SY of Interface carpet tile in 2nd floor Conference & Tenant Lounge (Speakeasy)

Suppliers:

Tarkett
MAPEI Corporation
XL Brands